[ANNOUNCE] Current SRU cycle extended by 1 week

Seth Forshee seth.forshee at canonical.com
Mon Oct 24 21:36:41 UTC 2016


As a result of the recent kernel update for CVE-2016-5195 and the
subsequent respin of all -proposed kernels, it has become necessary to
extend the current SRU cycle by one week in order to complete testing
and verification. The kernels currently in -proposed will be released on
Nov 7 rather than Oct 31 as originally planned.

The updated schedule for the next SRU cycle is as follows:

cycle: 04-Oct through 26-Nov
====================================================================
         04-Nov   Last day for kernel commits for this cycle
07-Nov - 12-Nov   Kernel prep week.
13-Nov - 25-Nov   Bug verification & Regression testing..
         28-Nov   Release to -updates.

Seth