SRU cycle 2022.01.03 extended through Jan-31

Kleber Souza kleber.souza at canonical.com
Fri Jan 7 11:23:45 UTC 2022


Due to regressions found with kernels released from the previous SRU cycle
affecting some amdgpu graphics [1] and AMD Secure Encrypted Virtualization (SEV)
[2], the start of the current cycle (2022.01.03) has been delayed and therefore
this cycle is going to be extended by a week with the following new schedule:

cycle: 03-Jan through 30-Jan (4 weeks)
====================================================================
          29-Dec   Last day for kernel commits for this cycle.
03-Jan - 07-Jan   Kernel prep week.
10-Jan - 28-Jan   Bug verification & Regression testing.
          31-Jan   Release to -updates.

The new schedule for the next SRU cycle is as follows:

cycle: 31-Jan through 20-Feb (3 weeks)
====================================================================
          26-Jan   Last day for kernel commits for this cycle.
31-Jan - 04-Feb   Kernel prep week.
07-Feb - 18-Feb   Bug verification & Regression testing.
          21-Feb   Release to -updates.


The up-to-date SRU cycle dates can also be found at
https://kernel.ubuntu.com/.


[1] https://bugs.launchpad.net/ubuntu/+source/linux/+bug/1956401
[2] https://bugs.launchpad.net/ubuntu/+source/linux/+bug/1956575